1 question with a worked solution

  1. 6 workers take 12 days to complete constructing a boundary wall. How many days will it take for 9 workers working at the same rate to complete the same wall?
    1. A) 6 days
    2. B) 9 days
    3. C) 10 days
    4. D) 8 days
    Check my answer

    Correct answer: D) 8 days

    Work is inversely proportional: Total man-days = 6 workers × 12 days = 72 man-days. Days required by 9 workers = 72 / 9 = 8 days.

    Show worked solution
    Step 1: Calculate total work in man-days: Work = Workers × Days = 6 × 12 = 72 man-days. Step 2: Relate work to new workforce: 9 × Days = 72. Step 3: Solve for Days: Days = 72 / 9 = 8 days. Answer: 8 days.
    Modelled on: the O/L Mathematics examination pattern

Get this auto-marked

Next in the syllabus

Where does Inverse Proportion fit in the syllabus?

Grade 10 · Term 1

Practise Inverse Proportion questions today

Free AI study coach, daily plans and practice questions. No payment required.

Create Free Account Free Quiz